Works on the extensive refurbishment of Ta’ Kerċem Primary School are progressing well, in line with the agreed programme.

Major works have now been practically completed, including the restoration of the old façade, the construction of the new lift shaft, installation of electrical and water services, fire and intruder alarm systems, plastering, tile laying, soffit works, and wall painting. The new school furniture has also been delivered.

FTS will be finalising the remaining internal works on the main hall over the coming weeks.

Ta’ Kerċem Primary School will be ready to reopen its doors for the new scholastic year, providing students and educators with a modernised and improved learning environment.